No sample with the tender, yet an interest: the Council of State lets Neorec still challenge the federal police specifications at the award stage
For the illuminated police signs, Neorec submitted a tender without the samples the specifications required ‘on pain of absolute nullity’, was promptly declared irregular and then challenged the award to The Neon Company; the Belgian State argued that Neorec had no interest and should have challenged the specifications straight away, but the Council of State follows its Labonorm case law, reads the Court of Justice’s Grossmann judgment narrowly and declares the action admissible.
What happened?
In the Bulletin der Aanbestedingen of 23 August 2002, the federal police procurement service launched a general call for tenders for a three-year open agreement for the purchase of illuminated signs, in four items: about 127 double-sided and 8 single-sided signs for the federal police, and about 546 double-sided and 130 single-sided signs for the local police. Point 5.8 of the specifications required, ‘on pain of absolute nullity of the tender’, that bidders submit three samples for items 1, 2 and 4 at the latest by the opening of tenders. On 16 September 2002 Neorec wrote to the police that, for three reasons, it could not meet that requirement. It nevertheless submitted a tender on 7 November 2002, with the express reservation that its price was, ‘in departure from your request’, not accompanied by prototypes, because the required investment was cautiously estimated at 18,500 euros. Besides Neorec, The Neon Company and Petrus also tendered. The award report of 27 November 2002 found that Petrus and Neorec had not supplied samples, declared their tenders irregular and proposed to award the contract to The Neon Company. Neorec was informed on 16 December 2002 that its tender had not been taken into consideration because of the missing sample, requested the reasoned decision the next day and received it on 18 December. On 14 February 2003 it sought annulment of the award to The Neon Company and of the declaration that its own tender was irregular. Before the Council of State, everything first turned on admissibility. The Belgian State argued that Neorec had no interest: its tender was irregular, so even after an annulment it could never obtain the contract. The Council rejected that. If a plea alleging the unlawfulness of the sample requirement succeeds, the res judicata effect of the judgment means the contracting authority must disapply that clause — and then the ground for the irregularity falls away as well. In its last brief the State added a second objection, based on the auditor’s report and the Court of Justice’s Grossmann Air Service judgment of 12 February 2004: anyone who considers the specifications discriminatory must challenge them immediately rather than wait for the award, and failing to do so is careless. Neorec relied on the Labonorm judgment of the general assembly of the Council of State (no. 152.173 of 2 December 2005), under which the possibility of challenging the specifications immediately does not prevent their unlawfulness from also being invoked against later decisions. The Council sided with Neorec. In Grossmann, the Court had only answered for the cumulative case of a person who neither challenged the specifications nor took part in the procedure — Neorec did tender. Moreover, the Court only said that Member States may introduce such a restriction, not that they must. The Labonorm line fits within that, and is also in keeping with the Court’s judgment in Commission v Ireland of 28 January 2010, holding that national time limits may not deprive the right to challenge award decisions of its effectiveness. Relying on the theory of the complex administrative operation is therefore not careless, although the Council left the door open to a different view if the specifications themselves had required visible legality objections to be reported immediately. The action is admissible. Since the auditor’s report had only examined admissibility, the Council reopened the proceedings and instructed the auditor’s office to carry out a further investigation on the merits.
Why does this matter?
The judgment settles a question every bidder facing a difficult clause asks: must I challenge the specifications immediately, or can I take part and attack the clause later if it costs me the contract? In 2010 the Council of State, in line with Labonorm, answered that the latter was possible. Two lessons reach beyond these signs. First, an irregular tender does not automatically deprive a bidder of its interest. If the irregularity flows precisely from the clause it considers unlawful, an annulment can benefit it, because the authority may then no longer apply that clause. Second, the Council read Grossmann strictly — EU law permits an exclusion but does not impose one, and Grossmann concerned someone who had not even tendered. Neorec, moreover, did not stay silent: it raised its objection in writing beforehand and repeated it in its tender. Anyone reading this judgment today should know it is a snapshot. It predates the Act of 17 June 2013, and the Council would later, also citing Grossmann and the Court’s eVigilo judgment, take a stricter view of bidders who hold back their criticism of the documents. It is also an interim judgment: it says nothing on whether the sample requirement itself was unlawful.
The lesson
For bidders: under the Labonorm case law, you did not necessarily have to challenge a clause you consider unlawful straight away in order to invoke it later — but do make your objection known in time and in writing, as Neorec did, and bear in mind that case law has since become stricter. If you want to be safe, challenge an exclusionary clause as soon as possible today. Nor should you expect an irregular tender to make your action automatically inadmissible: if the irregularity flows from the clause you challenge, you have an interest. For contracting authorities: you will not win a lack-of-interest objection merely by pointing to the irregularity of the tender if that irregularity rests on the disputed clause itself. And if you want bidders to report objections to the specifications immediately, write that expressly into the procurement documents — the Council suggests this could change the assessment of diligence. Only impose a requirement such as ‘samples on pain of absolute nullity’ if you can justify its necessity and proportionality.
Ask yourself
As a bidder: did you report your objections to an exclusionary clause in writing to the authority before submitting? Do you know whether you must challenge that clause immediately or can still invoke it at the award stage — and are you taking into account that case law has tightened since 2010? Can you show that an annulment benefits you, even though your tender was declared irregular? As an authority: does the irregularity you invoke to contest the interest not rest precisely on the clause the bidder calls unlawful? Do your procurement documents require bidders to report visible legality objections without delay?
About this database
The Council of State (Raad van State / Conseil d'État) is Belgium's supreme administrative court. In disputes over public procurement — from contract awards to tenderer exclusions — the Council of State is the final arbiter. The rulings in this database are summarised by TenderWolf in plain language, with practical lessons for tenderers and contracting authorities. View all rulings →