Synductis withdraws the award before RDR Infra goes to the Council: the annulment action is pointless and the 53,870-euro damages claim fails
Synductis declared RDR Infra’s BAFO for lot 1 of a large contract for underground pipes and cables substantially irregular, withdrew that award after objections and then stopped the whole procedure; because the award had already been withdrawn when RDR Infra brought its annulment action, and the withdrawal gave it exactly what it sought with that action, the Council of State declares the action inadmissible and without object — and cannot even rule on the claimed compensation of 53,870.04 euros.
What happened?
Synductis, acting in the name and on behalf of its members — Farys, Fluvius System Operator (for the distribution system operators), IWVA, Pidpa, Proximus and the Agency for Roads and Traffic — tendered a works contract for the laying of underground pipes and cables, through a competitive procedure with negotiation with prior call for competition, published in the Bulletin der Aanbestedingen of 8 October 2019. The contract had three lots: sites without water outside Limburg (lot 1), sites with water works by Farys (lot 2) and sites without water in Limburg (lot 3). 67 tenders were received; RDR Infra bid for lot 1. On 28 August 2020 the board of Synductis approved the award report: RDR Infra’s tender was declared substantially irregular and lot 1 was awarded to 21 companies, each for a share. RDR Infra and another bidder, Wagro, lodged written objections, notably on the price examination and the statement of reasons, and went to the Council of State. After an internal review by the Purchasing and Legal departments of Fluvius System Operator, Synductis withdrew the award for lots 1 and 2 on 24 September 2020, since it appeared ‘at least on certain grounds contestable’; the award for lot 3 had already been withdrawn on 10 September 2020. By judgment no. 248.562 of 13 October 2020 the Council therefore dismissed RDR Infra’s application for suspension under extreme urgency for lack of object. On 23 October 2020 Synductis stopped the entire award procedure following a complaint about the lack of a European publication, which RDR Infra learned by registered letter of 29 October 2020. That same day, 29 October 2020, RDR Infra brought an annulment action against both the award decision and the withdrawal decision, together with a claim for compensation of 53,870.04 euros plus compensatory interest from 28 August 2020. Its reasoning: without a finding that the award was unlawful there can be no compensation under article 11bis of the Council of State Act, so the withdrawal — taken, it said, precisely to avoid compensation — also had to be annulled. The Council, following the concurring opinion of first auditor Frederic Eggermont, did not accept that reasoning. The action against the withdrawal is inadmissible for lack of interest: the withdrawal gave RDR Infra exactly what it sought with its action against the award, namely a new chance at the contract and the disappearance of the negative assessment of its BAFO. An authority can hardly be blamed for removing from the legal order a decision whose lawfulness it doubts itself. The action against the award is without object, and has been from the outset: the award had already been withdrawn on 24 September 2020 when the action was brought on 29 October 2020. The case law obliging the Council to examine the pleas with a view to compensation concerns situations where interest is lost during the proceedings, and does not apply here. Nor do article 14 of the Act of 17 June 2013 (‘has or has had an interest’) or the right of access to a court (article 13 of the Constitution) help RDR Infra: any other harmful effects can be brought before the ordinary courts. With no unlawfulness established, the compensation claim is also dismissed. Both parties asked for the maximum procedural indemnity of 2,800 euros, but the Council awarded Synductis the indexed basic amount of 770 euros: the case was not complex enough and the Council is not bound by the parties’ concurring view. RDR Infra bears the 200-euro roll fee, the 20-euro contribution and those 770 euros; the 200-euro fee and the 20-euro contribution for the compensation claim are refunded to it.
Why does this matter?
The judgment shows the flip side of withdrawal as a ‘disguised annulment’. When an authority withdraws a contested award while an annulment action is already pending, the bidder can recover its costs, as later judgments show. But a bidder who only brings its annulment action after the award has been withdrawn is left empty-handed: the action against the award is without object from the start, and the action against the withdrawal itself fails for lack of interest, because the withdrawal produces precisely the result the bidder was after. The Council thereby also closes the route to compensation under article 11bis of the Council of State Act: that requires a judgment finding unlawfulness, and no such judgment is forthcoming. The argument that an authority withdraws in order to escape a damages claim makes little impression on the Council — an authority that corrects a doubtful decision itself acts, in principle, properly. For bidders, the damages debate then shifts to the ordinary courts. Finally, the judgment is a useful reminder on the procedural indemnity: in procurement cases too, the indexed basic amount (here 770 euros) is the rule, and even a joint request by both parties for the 2,800-euro maximum does not bind the Council.
The lesson
If you are a bidder and the authority withdraws an award you are challenging, realise that the withdrawal usually gives you what an annulment action would achieve: a new chance at the contract and the removal of a negative assessment. An annulment action against the withdrawal, solely to keep open the route to compensation before the Council of State, has little prospect of success. If you want to recover losses — for example the cost of your tender and BAFO — look to the ordinary courts, and seek advice in good time. Also check whether the withdrawal is followed by a termination or new decision that does affect you; that may then be the decision to challenge. For authorities, the judgment confirms that a timely withdrawal of an award that appears ‘at least on certain grounds contestable’ is a legitimate and effective way out, as long as the conclusion of the contract has not yet been notified. And anyone seeking an increased procedural indemnity must explain concretely why the case is particularly complex; referring to ‘the great technicality’ is not enough.
Ask yourself
Do you know when the authority withdrew the award, and whether your action was brought before or after? Do you realise that a withdrawn decision is deemed never to have existed, so that an action against it is without object? If you want to recover losses, have you considered whether the ordinary courts are the appropriate route rather than the Council of State? Do you follow up whether the withdrawal is followed by a termination or new award, and do you challenge that decision if it harms you? And as an authority: do you withdraw an award whose lawfulness you doubt in good time, before the conclusion of the contract has been notified, and do you support a request for an increased procedural indemnity with concrete, case-specific arguments?
About this database
The Council of State (Raad van State / Conseil d'État) is Belgium's supreme administrative court. In disputes over public procurement — from contract awards to tenderer exclusions — the Council of State is the final arbiter. The rulings in this database are summarised by TenderWolf in plain language, with practical lessons for tenderers and contracting authorities. View all rulings →