A stamped envelope beats a ‘lost’ bid: the Berchem-Sainte-Agathe CPAS mislays Multipharma’s tender and the award to Pharma Force is suspended
The Council of State suspended, under the extreme urgency procedure, the award of the medicine supply for the ‘Val des Fleurs’ care home to Pharma Force, because Multipharma proved with an envelope stamped by the CPAS (‘received on 22 April 2022 at 13:40’) that it had submitted a bid on time, which the CPAS then lost — the award therefore rested on the factually incorrect ground that only two bids had been received and breached the equal treatment of tenderers; the claim against the implicit refusal to award the contract to Multipharma itself was, however, inadmissible.
What happened?
On 30 March 2022, the social welfare council of the CPAS of Berchem-Sainte-Agathe decided to launch a contract for the ‘supply of medicines and pharmaceutical specialities through individual medication preparation (PMI)’ for its ‘Val des Fleurs’ nursing and care home. The contract, estimated at 173,553.72 euros excl. VAT for three years, was awarded through a negotiated procedure without prior publication; six operators were consulted, including Multipharma and Pharma Force. The sole award criterion was price, expressed as a discount on the public price. The specifications (SCAD 974 – 30/03/2022) required a paper bid ‘in a definitively sealed envelope’ bearing the specifications reference, to be sent by post or delivered by hand, by 22 April 2022 at the latest. Multipharma states that its employee handed in the bid — offering a 35% discount — in person at the CPAS that day at 13:40. As a receipt, it was given back a copy of the envelope bearing the CPAS address, the CPAS stamp, the date and time of delivery and the note ‘Multipharma Besteknummer: SCAD 974-30/03/2022’. Yet the evaluation report of 8 June 2022 stated that only ‘2 companies submitted a bid’: Pharma Force and Lloydspharma Group, each initially offering a 30% discount. After negotiations, Pharma Force offered 35%, and on 13 July 2022 the CPAS awarded it the contract. Multipharma was not informed. Concerned because performance was due to start on 1 August 2022, it phoned the purchasing department on 22 July 2022 and learned that the contract had already been awarded. In a phone call on 26 July, it emerged that the CPAS had lost its bid and could not find it; at the CPAS’s request, Multipharma handed in a duplicate on 28 July. Only by letter of 21 September 2022 — sent by registered mail on 23 September and by e-mail on 4 October — did it receive formal notice of the award, together with the evaluation report. On 7 October 2022, Multipharma sought suspension under the extreme urgency procedure of both the award and the implicit decision not to award the contract to it. The Council declared the second claim inadmissible. An unsuccessful tenderer can only challenge such an implicit refusal if it convincingly shows that the contract had to be awarded to it. That was not the case here: although Multipharma offered the highest initial discount at 35%, it was not certain that the CPAS would have awarded on the basis of the initial bids without negotiating, nor that Multipharma would have submitted the best ‘BAFO’ after negotiations — it used the conditional tense itself. Moreover, the CPAS had never examined its selection or the regularity of its bid, and the Council cannot substitute its own assessment for that of the contracting authority. On the award itself, however, the Council was clear. The stamped envelope showed prima facie that Multipharma had submitted a bid on time, all the more so since the specifications allowed delivery by hand, required a definitively sealed envelope (so that its content cannot be established afterwards) and prescribed exactly the references that appeared on the envelope. The CPAS did not dispute the value of that document and left the matter to the Council’s discretion. Neither the award decision nor the administrative file explained what had happened to the envelope. The award thus rested on the factually incorrect ground that there were only two bids, and Multipharma was not treated equally with the other tenderers. To that extent, the plea was serious. The Council disregarded the criticism of the CPAS’s conduct after the award (the lack of response after the duplicate): the legality of a decision is assessed at the time it was taken. The Council suspended the award to Pharma Force, ordered the immediate enforcement of the judgment, kept Multipharma’s bid (exhibit A) confidential and reserved the costs.
Why does this matter?
A contracting authority losing a bid sounds like an anecdote, but with paper submissions it is a real risk — and this judgment shows how decisive the burden of proof then becomes. Multipharma did not win because it could explain the loss, but because it could disprove the finding of ‘only two bids’ with a single document: the stamped copy of its envelope, with date, time and specifications reference. Against that evidence stood a CPAS with no explanation whatsoever about the fate of the envelope, which left the matter to the Council. Two lines in the judgment reach beyond this case. First: an award decision that ignores a bid submitted on time rests on a factually incorrect ground and breaches the equal treatment of tenderers — even without bad faith. Second: whoever asks for more than the suspension of the award, namely a finding that they should have won the contract, must show that the contracting authority had no other choice. In a negotiated procedure where selection and regularity of the bid were never examined, that is almost impossible. Subsequent events confirm the approach: in judgment no. 258.093 of 1 December 2023, the Council annulled the award to Pharma Force.
The lesson
Tenderers: if you hand in a paper bid in person, always obtain a receipt with date, time, stamp and specifications reference — or, as Multipharma did, have a copy of the envelope stamped. Also keep a full copy of the bid submitted. If you hear nothing as the start date approaches, get in touch yourself: Multipharma only discovered the problem by phoning. As a rule, ask for suspension of the award; the additional claim against the implicit refusal to award to you only succeeds if you can prove the contract inevitably had to go to you. Contracting authorities: log every incoming bid on receipt in a register with date and time, and check the number of envelopes against that register at the opening. A lost bid is your risk, not the tenderer’s, and an evaluation report stating ‘only two bids’ when three were delivered will not stand. If a tenderer produces proof of submission after the award, consider withdrawing the award and re-evaluating the bids, rather than simply sending the old report.
Ask yourself
Do you have a dated and stamped receipt with the specifications reference for every paper bid? Do you keep a full copy of every bid submitted, so you can produce it immediately if it is lost? Do you actively follow up when you hear nothing about a contract whose performance is approaching? Can you show that the contract necessarily had to be awarded to you, or should you only ask for suspension of the award? As a contracting authority: do you keep a receipt register and check at the opening that all registered envelopes are present? As a contracting authority: how do you respond when a tenderer proves after the award that it submitted on time?
About this database
The Council of State (Raad van State / Conseil d'État) is Belgium's supreme administrative court. In disputes over public procurement — from contract awards to tenderer exclusions — the Council of State is the final arbiter. The rulings in this database are summarised by TenderWolf in plain language, with practical lessons for tenderers and contracting authorities. View all rulings →