RTBF’s own departments launched a 1.3 million euro kitchen contract: ratification by the standing committee after the fact does not save the award to Sotrelco
After the contractor for its kitchens in Media Square went bankrupt, RTBF had its own departments hastily launch a new negotiated procedure without prior publication, although only the standing committee was competent for contracts of 400,000 euros or more; because such a lack of competence cannot be cured afterwards, the Council of State, at the request of third-ranked AM Expert Construct, suspends the 1,305,465.66 euro award to Sotrelco.
What happened?
In July 2025 RTBF’s standing committee authorised a contract for the technical finishing works for two professional kitchens in Media Square, the public broadcaster’s new headquarters. On 17 October 2025 the board of directors approved the award of the five lots; lots 1 to 4 went to Space Design – Aménagement Construction Immobilier Group. On 24 February 2026 that company announced that it had filed for bankruptcy. The works came to a halt, and with them the opening of the staff restaurants and the work of the lot 5 contractor, the kitchen equipment supplier and the caterer. RTBF terminated lots 1 to 4 and launched a new contract (ref. PNSPP2026.010) through a negotiated procedure without prior publication on grounds of extreme urgency, and without division into lots. On Friday 27 February 2026 invitations went out to six companies, with a tender deadline of 11 March. Requests for more time were initially refused; after the mandatory site visit on 4 March the deadline was eventually moved to 17 March 2026. Three companies submitted a tender: AM Expert Construct, Entreprises Simonis and Sotrelco. After a round of improved offers on price and planning, AM Expert Construct came third. On 24 March the director-general decided to award the contract to Sotrelco for 1,305,465.66 euros excluding VAT; the standing committee, consulted electronically between 24 and 26 March, recorded that ‘le marché est accepté’. Since no standstill period applied, Sotrelco started work immediately. On 10 April 2026 AM Expert Construct sought suspension under the extreme urgency procedure. Its first plea: there was no decision by a competent body to launch the contract. RTBF argued that AM Expert Construct had suffered no harm, since the standing committee had approved everything afterwards and the procedure would otherwise have been exactly the same. The Council rejects this: such reasoning prejudges what the competent body would have decided had it been consulted in time, and that is precisely why, according to settled case law, a lack of competence cannot be cured by subsequent ratification. The objection that the complaint came too late also fails. No launch decision had ever been communicated to the bidders; there was not even one in the administrative file. AM Expert Construct only became suspicious when the award decision made no reference to any launch decision in its preamble, and a bidder cannot be expected to scrutinise every preparatory act and go to court straight away. On the merits, the director-general’s notes of 2 and 24 March 2026 showed that ‘la direction des Facilités, en concertation juridique avec le service Marchés publics’ had decided to re-tender the contract. Those departments are not competent for any amount; from 400,000 euros excluding VAT, competence lies with the standing committee under Article 7 of the internal rules. There was no force majeure, and the rules specifically allow the standing committee to meet electronically in urgent cases, which RTBF did for the award. The argument that the new contract was a continuation of the old one is equally unconvincing: it differed substantially through the negotiated procedure without publication, the removal of the lots and the choice of award criteria. Moreover, the specifications were amended after 4 March, precisely on the second award criterion on which AM Expert Construct lost the contract. The lack of competence taints the entire procedure and the award. RTBF showed no adverse consequences of a suspension. The Council suspends the award decision of 24 March 2026, orders immediate enforcement of the judgment and reserves the costs.
Why does this matter?
Urgency is no licence to skip internal rules of competence. RTBF faced an understandable problem — a bankrupt contractor and a new headquarters without working kitchens — and took the fastest route: the departments launched the procedure, and the standing committee would sign later. The Council of State reiterates that a lack of competence cannot be regularised afterwards, because no one can know what the competent body would have decided had it been consulted beforehand. That is not a theoretical objection here: the new contract differed from the old one on essential points (procedure, lots, award criteria), and the specifications had been changed after the information note to the standing committee, on the very criterion that proved decisive. The procedural findings are just as important. The Council accepts that an interest in the plea is required even for a rule of public policy such as competence, but holds that a lack of competence at the launch stage in itself creates a sufficient risk of harm. And, expressly referring to the Court of Justice’s case law in Grossmann, eVigilo and Cooperativa Animazione Valdocco, it refuses to require bidders to challenge every preparatory decision immediately on pain of being time-barred: absent an express statutory scheme, criticism of the launch decision remains possible in the action against the award, especially where that decision was never communicated. The fact that the works were already well under way did not prevent the suspension.
The lesson
For contracting authorities: for every contract, check which body is competent under your statutes or internal rules to launch the procedure, and make sure that decision is on record before the invitation to tender, together with the amount that determines the competence threshold. Extreme urgency justifies a faster procedure, not bypassing the competent body; if your rules provide for an urgent electronic meeting, use it at the launch stage and not only for the award. If you amend the specifications after informing the competent body, submit the amendment again. Refer to the launch decision in the preamble of your award decision and include it in the administrative file. For bidders: read the preamble of the award decision as carefully as the scoring table. If there is no reference to a launch decision, or the amount exceeds the threshold of the body that signed, that is a serious plea — even if you took part in the procedure without objection and it seems too late to challenge the preparatory acts.
Ask yourself
As an authority: which body is competent under your statutes to launch a contract of this value, and is there a formal decision of that body before the invitation to tender? In cases of extreme urgency, do you use the urgent procedures of your own rules for the launch decision, and not only for the award? Have you resubmitted amendments to the specifications made after approval to the competent body? As a bidder: does the award decision refer to a launch decision by a competent body, and does that competence match the contract value? Have you checked the administrative file for that launch decision?
About this database
The Council of State (Raad van State / Conseil d'État) is Belgium's supreme administrative court. In disputes over public procurement — from contract awards to tenderer exclusions — the Council of State is the final arbiter. The rulings in this database are summarised by TenderWolf in plain language, with practical lessons for tenderers and contracting authorities. View all rulings →