Rejection French-speaking chamber

Challenging a tender as 'tailor-made for incumbent X' fails when the harm comes from a clause you did not actually attack

Ruling nr. 251367 · 12 August 2021 · VIe vakantiekamer

The Council of State rejects routing-services provider Easypost's suspension request against the IPFBW postal-services tender because the alleged harm in fact stems from the broader requirement that affiliated entities pre-frank their own mail — a requirement Easypost did not actually challenge — rather than from the cumulative obligation to offer two franking methods (stamp + franking machine) that it did challenge.

What happened?

On 9 July 2021, the Walloon Brabant intermunicipal financing entity IPFBW published a European framework tender for postal services covering the municipalities, social welfare centres and other public entities of Walloon Brabant — a 48-month framework agreement worth an estimated EUR 2 million excl. VAT. The tender (ref. SEDIFIN-MP-IPFBW/PO/Services postaux/2021) defined the scope as 'universal postal services' under Article 15 of the Belgian Postal Act of 26 January 2018, without division into lots, requiring four franking methods to be supported — two of them cumulatively to be performed by the affiliated entity itself (stamps and franking machine), with operator-side franking offered only as a 'mandatory option'. Postalia Belgium, trading as Easypost — a routing services provider that collects, sorts and pre-franks mail for ultimate delivery by bpost — filed a 25 July 2021 extreme-urgency suspension request. Its single plea contained four critiques: (1) the cumulative stamp-and-franking-machine obligation could de facto only be met by bpost; (2) a 10 km radius access-point requirement was tailored to the bpost network; (3) the motivation for not splitting the contract into lots was inadequate; (4) the inventory failed to provide separate line items for processing fees and franking value. Before the 6 August hearing, IPFBW's board adopted amendments to the tender on 4 August. At the hearing Easypost withdrew its second and fourth critiques. The Court rejected the first critique on two grounds: first, the alleged harm — being unable to bid based on a routing model where the operator franks — flowed not from the cumulative obligation Easypost attacked, but from the more general pre-franking-by-the-affiliated-entity rule, which Easypost had not challenged. Second, Easypost demonstrated only that the conditions did not match its commercial model, not that they made participation impossible. The third critique was rejected because the choice not to allot is discretionary, subject only to marginal review for manifest error, and IPFBW had set out its main reasons (process integration, administrative load, environmental impact). Suspension request rejected, costs awarded to IPFBW.

Why does this matter?

Many tender challenges rely on the narrative 'this tender is tailored to the incumbent'. This ruling shows sharply that such an argument only succeeds if it is technically precise. The Court does not assess whether the tender is generally biased; it asks whether the specific clause you attacked is the cause of your alleged exclusion. Attacking the wrong clause — e.g. a cumulative obligation when the real source of harm is the general pre-franking rule — loses, even if the underlying narrative is correct. Aim your plea at the exact clauses that produce the exclusion, and demonstrate concretely that the clause makes your participation impossible — not merely inconvenient.

The lesson

If you want to suspend a tender for unlawfully restricting competition, identify exactly which clause excludes you and aim your plea at that clause. Exclusion flowing from clause X cannot be attacked with a plea against clause Y. Show concretely that the clause makes your participation impossible — not just incompatible with your preferred business model. And on lot-splitting motivation: the contracting authority only needs to state the main reasons, not pre-empt every conceivable counter-argument.

Ask yourself

Bid manager: before filing an extreme-urgency challenge against a 'tailor-made' tender, ask yourself — can I point to exactly which clause excludes me, and can I show I would actually bid if it were removed? If not, or if the real pain is in a different clause than the one you attacked, you are weak. Contracting authority: when you do not allot, list at least three coherent main reasons (operational, administrative, environmental) in the tender itself. That satisfies Article 58 and keeps you on the right side of marginal review.

About this database

The Council of State (Raad van State / Conseil d'État) is Belgium's supreme administrative court. In disputes over public procurement — from contract awards to tenderer exclusions — the Council of State is the final arbiter. The rulings in this database are summarised by TenderWolf in plain language, with practical lessons for tenderers and contracting authorities. View all rulings →